Rosatom's Own Schedule Has Been Leaked: Paks II May Be Delayed Even Further.
8 Articles
8 Articles
The paper obtained an Excel spreadsheet with thousands of pieces of data showing the construction schedule.
The handover of Paks II may be delayed by two years: according to Rosatom's internal construction schedule, the entire project will be ready for test operation on December 30, 2034, not in 2032, writes Politico, based on internal documents obtained by it.
The Brussels-based newspaper Politico has presented another document without a verified background.
According to Rosatom's internal schedule, the completion of the Paks II nuclear power plant could be delayed by at least two years. According to a document obtained by Politico, the Hungarian ...
The last new reactor can only be delivered at the end of 2034, so Paks II. can start in 2035. The post Politico: Paks II. further delayed according to internal Rosatom document first appeared on 24.hu.
Former Minister of Foreign Affairs and Trade Péter Szijjártó said this year that the investment is expected to be completed between 2031 and 2032. It doesn't seem like it.