Breakthrough in Mumbai-Ahmedabad Bullet Train Project: Tunnel Section Completed
VALSAD DISTRICT, GUJARAT, JUL 10 – The Daman Ganga bridge is the 16th of 25 planned bridges on the 508-km Mumbai-Ahmedabad corridor, advancing India’s first high-speed rail project, NHSRCL said.
- In a recent development, NHSRCL completed the 16th of 25 river bridges, including the final one in Valsad district, Gujarat, marking a key milestone in the Mumbai-Ahmedabad bullet train project.
- Built to enable uninterrupted high-speed connectivity across key industrial and residential zones in the Mumbai-Ahmedabad corridor.
- NHSRCL completed 16 of 25 river bridges, all in Valsad district near Vapi and Boisar, marking key progress in the bullet train project.
- NHSRCL officials say civil works are nearing key goals, boosting India's first high-speed rail project's progress.
- The Daman Ganga River bridge in Valsad, Gujarat, was recently completed by NHSRCL, marking the 16th of 25 planned spans, advancing India’s first high-speed rail project.
11 Articles
11 Articles
2.7 km long continuous tunnel completed with first breakthrough in 21 km tunnel between BKC and Shilphata
On July 9, the first breakthrough was achieved in the 21 km long tunnel being constructed between Bandra-Kurla Complex (BKC) and Shilphata in Maharashtra, marking the successful completion of a 2.7 km continuous tunnel section. Out of the total 21 km tunnel, 5 km is being constructed using the New Austrian Tunnelling Method (NATM) between Shilphata and Ghansoli, while the remaining 16 km will be built using Tunnel Boring Machines (TBMs). The tun…
Mumbai-Ahmedabad bullet train gets a breakthrough: Mumbai-Thane portion of tunnel completed
The first breakthrough in the 21-km tunnel being constructed between Bandra-Kurla Complex (BKC) in Mumbai and Shilphata in Thane for the Mumbai-Ahmedabad bullet train project has been achieved, the National High Speed Rail Corporation Limited (NHSRCL) announced on Thursday. This marks a major milestone in India’s first high-speed rail initiative, which aims to significantly cut travel time between the two major financial centres. Milestone in NA…
Breakthrough in Mumbai-Ahmedabad Bullet Train Project: Tunnel Section Completed
Breakthrough in Mumbai-Ahmedabad Bullet Train Project: Tunnel Section Completed The Mumbai-Ahmedabad bullet train project has reached a significant milestone with the completion of a 2.7 km tunnel section. This segment lies between the Bandra Kurla Complex in Mumbai and Shilphata in Thane, as announced by the National High-Speed Rail Corporation Limited (NHSRCL) on Thursday.The tunnel breakthrough, marking the first in the 21 km long constructio…