Microsoft signs on for capacity at Pure DC data center in Finland
The 110MW first phase is part of a €1.5 billion project that Pure DC says is fully leased and designed to scale to 550MW.
- Pure Data Centres launched its 110MW AI campus in Sein, Finland, confirming the facility is fully leased. This initial phase represents a $1.7 billion investment, marking the firm's major entry into complex AI infrastructure.
- Wojtaszek has shifted the company's focus to larger assets in remote locations to diversify beyond centrally located sites. His team worked with local authorities in Finland for two years securing land, energy, and financing for the campus.
- Jaakko Kiiskil, mayor of Sein Municipality, said the project will bring around 3,000 construction jobs to the region. The site is capable of expanding to more than 550 megawatts, representing as much as 7.5 billion in investments.
- Microsoft Corp. is reportedly signed on to lease capacity at the new AI-ready site, though Pure Data Centres declined to name specific clients. The British ambassador to Finland, Laura Davies, called the investment the largest yet by a UK company in Finland.
- Seeking to diversify funding, Pure Data Centres plans to tap the Nordic bond market and eventually seek global sponsors. Owned by Oaktree Capital Management, the firm has more than 1GW of capacity live or under development across Europe.
12 Articles
12 Articles
Pure DC Launches One of Europe’s Largest Ever AI Infrastructure Projects: Phase 1 (110MW) of an over €7.5 Billion, 550MW AI Campus in Seinäjoki, Begins Fully Leased, with Planning & Power Already Secured
Seinäjoki campus The campus positions Finland at the forefront of Europe’s AI revolution, creating opportunities for innovation, education, entrepreneurship and sustainable...
In the first phase, a 110 megawatt data center will be built in Seinäjoki.
The first phase will see the construction of a 110 megawatt data center, costing 1.5 billion euros. Construction has already begun.
Pure DC Building Finland AI Data Center, Secures Microsoft Deal
Oaktree Capital Management-backed UK firm Pure Data Centres is building a data center in Finland that clients including Microsoft Corp. are slated to use, part of a broader effort to ramp up the digital infrastructure necessary for Europe to build and run more artificial intelligent systems.
Pure DC signs potential £6.4bn European deal
Pure Data Centres Group has launched what will become one of Finland’s largest ever inward investment projects, and the largest ever by a UK company. Phase 1 will see investment of over £1.3 billion for a 110MW AI campus, with the site in Seinäjoki capable of scaling to a £6.4bn, 550MW+ campus for AI workloads, subject to the necessary permissions and contracting. The full Seinäjoki campus will be one of Europe’s largest ever AI infrastructure …
Coverage Details
Bias Distribution