Village of Red Hook acknowledges problems at sewer plant
RED HOOK, N.Y. — Improper installation of wastewater treatment equipment caused the smell residents along a creek used for sewage effluent are complaining about, village trustees say. Because of that contention, the Village Board decided to hold back $9,612.86 from the final payment to contractor Carver Construction, which oversaw the installation. The payment was authorized during the board’s meeting on Thursday, March 27. “A dispute arose … re…