Major Oakleigh trail link work begins
1 Articles
1 Articles
Major Oakleigh trail link work begins
The City of Monash will start work on a new bi-directional bike lane next month to link the Djerring and Scotchmans Creek trails through Oakleigh. In planning and development since 2022, the vital connection comprises a new bike facility along Atkinson Street to be completed by December. From Dandenong Road to Burlington Street the project will deliver a two-way bike lane on the east side of the street, 3m wide, separated from traffic by a 0.5m …