Published 1 month ago • loading... • Updated 1 month ago
Federal court rejects Trump order keeping Michigan coal plant open
The court said the Energy Department lacked an actual emergency and noted the plant has cost Midwest families $600,000 a day.
On Friday, the District Circuit Court for Columbia overturned the Energy Department's "emergency" order that forced the 64-year-old Campbell coal-fired power plant in Michigan to remain open past its scheduled retirement date.
Appeals Court Judge Cornelia Pillard wrote for the unanimous panel that the Federal Power Act allows such orders only as a "narrow, last-resort backstop," finding the Energy Department exceeded its authority when issuing the May 2025 order.
Since the order was issued, Campbell has cost families in the Midwest $600,000 a day, while the Sierra Club's "Burning Money" tracker estimates these administration orders have cost Americans over $546 million to date.
Ted Kelly, U.S. clean energy director at the Environmental Defense Fund, said the ruling rejected the Trump Administration's nationwide effort to force "unreliable, aging coal plants that are bleeding money and polluting communities to stay online."
This Michigan case is one of several legal disputes emerging across the country as the Trump Administration uses emergency powers to force a half-dozen coal-fired plants from closing, signaling broader challenges ahead.