New Demerara River Bridge 90.7% Complete as Cement Poured on Final Tower

Summary by Guyana Times
– on track for August 31 deadline The cement was poured on the final of 35 concrete towers on Saturday night, marking a significant milestone in the construction of the new Demerara River Bridge and moving closer towards the August 31, 2025 deadline. In fact, construction works are approximately 90.7 per cent completed. This was revealed by Public Works Ministers, Juan Edghill, and Deodat Indar who joined local engineers, the contractor: China R…
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.

4 Articles

All
Left
Center
Right
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • There is no tracked Bias information for the sources covering this story.
Factuality

To view factuality data please Upgrade to Premium

Ownership

To view ownership data please Upgrade to Vantage

Guyana Chronicle broke the news in on Sunday, June 8, 2025.
Sources are mostly out of (0)

Similar News Topics