USD489 BOE approves three of four Change Orders, holds off on HHS Murals

Summary by The Hays Daily News
The USD489 Board of Education approved (4-3) three of the four Change Orders for the new Hays High School Bond Construction project, presented by Nabholz Construction's Senior Project Superintendent Brett Stevens and Project Manager Dylan Weddle. Stevens' presentation included the addition of a welding booth ($26,448), cooling tower check valves ($9,176), relocation of the track and field layouts ($37,064) and interior school murals ($38,374).