Breakthrough Achieved in 6.59-Km Tunnel of Rishikesh-Karnaprayag Rail Project
The 125-kilometer line is being built in Uttarakhand’s Rudraprayag district at a total cost of Rs 37,119 crore.
On Friday, Indian Railways achieved the breakthrough of 6.59-km-long Tunnel-14 on the Rishikesh-Karnaprayag Rail Project in Uttarakhand's Rudraprayag district, connecting the 4.7-km stretch from Portal-1 at Sumerpur and 1.79-km section from Portal-2 at Marora.
Engineers navigated complex geology using pre-excavation and multi-drifting techniques, while securing Portal-2 slopes with 30-35-metre-deep micropiles, 15-20-metre-long rock bolts, and consolidation grouting.
Rail Vikas Nigam Limited reported 79 per cent overall progress, with around 97 per cent of tunnel excavation work completed on the 125 km rail link featuring 16 tunnels and 19 bridges.
Union Minister for Railways Ashwini Vaishnaw termed the project a "lifeline to the future" for religious destinations Badrinath and Kedarnath, while Karnaprayag terminal station lies 123 kilometres from the India-China border.
Developed at a cost of Rs 37,119 crore, the project targets completion by December 2029, aiming to improve regional connectivity, facilitate Char Dham pilgrimage access, and strengthen national security.