Mapusa fruit ripening chamber to be operational in 15 days
NT Reporter Mapusa A fruit ripening chamber being built at the Mapusa sub yard market to provide a chemical-free method for ripening fruit is expected to be completed and operational within 15 days. The work, which was originally scheduled for completion by Ganesh Chaturthi, was delayed due to heavy rains and the pending electricity connection. The Mapusa sub yard market, one of the largest in North Goa, witnesses a huge demand for fruits, parti…