Lake Dalrymple Bridge Replacement To Start May 19th
Summary by Kawartha 411
1 Articles
1 Articles
All
Left
Center
Right
Lake Dalrymple Bridge Replacement To Start May 19th
KAWARTHA LAKES-Kawartha Lakes is moving forward with the full replacement of the Lake Dalrymple Bridge, with construction scheduled to begin May 19, 2025. This is a $4.7 million project in the 2025 Capital Budget to ensure state of good repair of City assets. The project will take place in three phases: Construction Preparation (May 19 to May 26, 2025): The contractor will mobilize equipment and prepare the site. During this time, sections of K…