Cabinet Approves ₹1.86 Lakh Crore Green Energy Corridor to Evacuate 135GW Renewable Energy
The scheme will add 50 GWh of battery storage and support evacuation of up to 135 GW of renewable power, officials said.
- On Wednesday, the Union Cabinet chaired by Prime Minister Narendra Modi approved the Green Energy Corridor Phase-III scheme, a Rs 1.86 lakh crore initiative to build transmission infrastructure for 135 GW of renewable power and deploy 50 GWh of Battery Energy Storage Systems.
- Expanding renewable generation requires shifting focus from capacity creation to transmission, storage, and supply. This scheme supports India's transition toward ambitious non-fossil capacity targets by helping integrate Renewable Energy into the grid.
- Greenfield Intra-State Transmission Systems projects will use Tariff Based Competitive Bidding, while brownfield upgrades follow a Cost Plus Basis. The State Transmission Utilities will manage implementation, supported by Rs 54,082 crore in Central Financial Assistance to reduce power costs.
- Deploying Battery Energy Storage Systems at developer ends addresses grid intermittency and peak-hour curtailment across States and Union Territories. This infrastructure will generate direct and indirect employment in power, manufacturing, and construction while benefiting end users.
- The scheme is targeted for completion by 2032-33, contributing to India's long-term energy security and ecologically sustainable growth. It will also foster skilled employment in operation, maintenance, and grid management across participating regions.
15 Articles
15 Articles
Cabinet approves ₹1.86 lakh crore Green Energy Corridor to evacuate 135GW renewable energy
Green Energy Corridor initiative will strengthen India’s Intra-State Transmission System to enable evacuation of up to 135 gigawatt (GW) of renewable energy across States/Union Territories
Cabinet clears Rs 1.86 lakh crore Green Energy Corridor-III to evacuate 135 GW renewable power
The Union Cabinet on Wednesday approved the Rs 1.86 lakh crore Green Energy Corridor Phase-III scheme to build transmission infrastructure for evacuation of up to 135 GW of renewable power and deploy 50 GWh of battery storage, as India prepares its grid for a sharp expansion in non-fossil energy capacity.
New Delhi, Sep 30 (IANS) The Union Cabinet chaired by Prime Minister Narendra Modi has approved the Green Energy Corridor Phase-III (GEC-III) scheme. This initiative will strengthen India's Intra-State Transmission System (INSTS), enabling the transmission of up to 135 GW of renewable energy between states and union territories. The scheme also provides for the installation of 50 GW of Battery Energy Storage Systems (BESS) at the renewable ener…
Cabinet approves Green Energy Corridor Phase-III scheme for Development of Intra-State Transmission System with Battery Energy Storage Systems
The scheme also provides for deployment of 50 GWh of Battery Energy Storage Systems (BESS) at the Renewable Energy (RE) developer/generator end or any other location of importance for grid flexibility to address intermittency, congestion, peak-hour curtailment and meet non-solar hour demand. The scheme will facilitate grid integration and power evacuation with in the States/UTs of India.
New Delhi: The central scheme to promote the renewable energy sector in the country has been launched. The Union Cabinet meeting chaired by the Prime Minister on October 30 approved the 'PM DHARA' scheme...