In Ille-Et-Vilaine, More than 6,000 Solar Panels Will Soon Be Installed on Wasteland
Summary by Le Télégramme
2 Articles
2 Articles
In Javené (35), near Fougères, a ground-based solar power plant is scheduled to enter service next July at a former embankment storage site. An investment of more than €3 million.
The construction of the ground-based photovoltaic plant will begin by early November 2025. The plant will be installed on a five-hectare wasteland plot along the RN12. Equipped with more than 6,000 photovoltaic modules, the plant will develop a power of 4 MW for an estimated production of 4.16 GWh per year.