ECRL to reach 90% completion by December 2025
The East Coast Rail Link (ECRL) project is on schedule to reach 90% completion by December this year, reported Bernama. The 665 km-long rail infrastructure project had recorded progress at 82.45% as of April 2025, said Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak. “Progress currently stands at 89% in Kelantan, 91% in Terengganu, 84% in Pahang, and 67% in Selangor. These figures reflect that the project is on course for full complet…