Building a Legacy June 2025 Construction Update
CLEMSON, S.C. — Neither heat nor rain are slowing down the excitement and momentum as the Harvey S. Peeler Jr. College of Veterinary Medicine continues to take shape. Here’s a quick summary of construction on each of our buildings. PCVM HUB The PCVM HUB is making great strides. The steel structure is complete, and work on miscellaneous steelwork will wrap up by the end of July. Crews will soon begin exterior framing and waterproofing, while roof…