£36 million Blairgowrie Recreation Centre project may have been sabotaged
Summary by Daily Record
2 Articles
2 Articles
Leaks delay Bam’s £36m Passivhaus leisure centre
Water ingress has caused a 34-week delay to the £36m build of a Passivhaus-standard leisure centre in Scotland. Bam Construct had expected to finish construction work at Blairgowrie Recreation Centre by 16 December last year, but the contractor only handed over to the local council… The post Leaks delay Bam’s £36m Passivhaus leisure centre appeared first on Construction News.