Prince Edward County and the contractor doing road work on County Road 3 have developed a plan to address unexpected issues that arose last week. As part of the road rehabilitation project, the existing asphalt surface was removed exposing the underlying granular road base. Once traffic was directed onto the temporary gravel surface, crews observed rapid deterioration caused by moisture within the road structure which resulted in rutting and une…