Underpass projects on Mall Road see 60% work
1 Articles
1 Articles
Underpass projects on Mall Road see 60% work
Construction work on two underpasses and an underground pedestrian route along Rawalpindi's Mall Road has reached 60 per cent completion, with traffic expected to resume on the corridor by June. Launched in mid-February 2025 under the supervision of Punjab's Communication and Works (C&W) Department, the projectexecuted by NESPAK and the Frontier Works Organisation (FWO)aims to create signal-free passage between TM Chowk and Mall Plaza Chowk, a…