Rovinari Wants to Transport Lignite with the Truck: without Enough Coal, the Oltenia Complex Could Close
5 Articles
5 Articles
The situation of the Oltenia Energy Complex continues to raise questions about the company's ability to support energy production under current conditions. MP AUR de Gorj, Ionelia Priescu, claims that the lack of coal in the warehouses is one of the problems facing the company. Parliament says that the company is asked to keep it in ... Article Ionelia Priescu: "The Oltenia Energy Complex has a real suffering. It no longer has coal.
The Ruvinari Thermocentre, the last large energy unit in the country, risks not being able to operate with the three active energy groups in the long term. The main problems are the lack of personnel and the lack of necessary coal, says former Director General of the Oltenia Energy Complex (CEO), Daniel Burlan, according to the local publication Actual in Gorj. "At Rovinari you can not go with three groups more than a few days and because they a…
Not enough lignite is arriving at Rovinari, it is likely that one of the blocks will have to be shut down.
According to Daniel Burlan, Rovinari could only work a few days with all three groups, and CE Oltenia transported 1.35 million tons of lignite in 2026.
Termocentrala Rovinari, which remained the only electricity production unit with significant installed power, risks not being able to operate with three long-term energy groups, according to statements by a former Director General of the Energy Complex (EC) Oltenia.
Coverage Details
Bias Distribution
- There is no tracked Bias information for the sources covering this story.
Factuality
To view factuality data please Upgrade to Premium


![[Opinion] Partial and Total Cuts of Manufactured Gas Affect Municipalities of Havana](/_next/image?url=https%3A%2F%2Fgrnd.b-cdn.net%2Finterests%2Fbcc24b7060085d1ebc4db4e6b8d92c71c3ca0c91.jpg&w=1440&q=75)