The Judge Orders to Analyze Adamuz's Black Boxes and the Ciaf Sees "Incongruities" in Welding Documents
11 Articles
11 Articles
The Court of Instance of Montoro number 2 has authorized the access, extraction and analysis of the contents of the black boxes of the two damaged trains on the past 18...
The Court of Appeal of Montoro, which investigates the Adamuz (Córdoba) railway accident, has authorized the dumping and analysis of the contents of the black boxes of the trains, which will take place this Thursday. Thus, the investigators of the Civil Guard who investigate the accident will be able to investigate all the details collected by the black boxes of the Alvia and Iryo trains involved in the fatal accident that cost the lives of 46 p…
The investigation maintains among the main hypotheses that the accident would arise from a problem in the railway infrastructure
The holder of the Court of Instance of Montoro, place number 2, has given the green light to the analysis of the black boxes of the trains damaged in Adamuz on 18 January. The judge has agreed that the dump and the extraction of its contents will take place on Thursday 5 March at the headquarters of the Commission for the Investigation of Railway Accidents (CIAF), according to legal sources. They state that the procedure will be carried out in t…
The Civil Guard has already asked the CIAF to detail these inconsistencies. The instructor also orders to analyze the recordings of the interior of the Iryo. More information: The Civil Guard "does not rule out" any hypothesis of the Adamuz disaster: sabotage, lack of prevention or "bad welding"
The Court of Justice of Montoro (Cordoba), number 2, has authorized access to, extraction and analysis of the black boxes of the two trains involved in the Adamuz accident of 18 January, which left 46 dead and more than 120 injured.
Coverage Details
Bias Distribution
- 60% of the sources lean Right
Factuality