PHOTO How the works on the Tecuci-Iași railway are progressing

Summary by Club Feroviar
The works on the Tecuci-Iași railway, which should have been completed in December, have reached an execution stage of 83%, a reason for pride for SRCF Iași. "During this period, ballasting works for the new switches in the Bârlad railway station and finishing works for the superstructure of the new track on the direct line II from the same station are in progress. The updated contractual deadline for completing the works on the railway superstr…
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.Cross Cancel Icon

1 Articles

The works on the Tecuci-Iași railway, which should have been completed in December, have reached an execution stage of 83%, a reason for pride for SRCF Iași. "During this period, ballasting works for the new switches in the Bârlad railway station and finishing works for the superstructure of the new track on the direct line II from the same station are in progress. The updated contractual deadline for completing the works on the railway superstr…

Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • There is no tracked Bias information for the sources covering this story.

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Club Feroviar broke the news in on Sunday, March 16, 2025.
Too Big Arrow Icon
Sources are mostly out of (0)
News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal