NICTD West Lake Corridor Project Update
The Northern Indiana Commuter Transportation District, operator of the South Shore Line, is providing an interim update on the completion of its new Monon Corridor service (also known as the West Lake Project). Previously we reported that the Design-Build contractor’s schedule anticipated a completion date of October 31, 2025, though we had hoped to work with the contractor to improve upon that date. Unfortunately, due to some unexpected rework …