Interview transcript:   Terry Gerton You’ve got an interesting case here. This is the first one you and I have talked about. That’s really DoD focused with the Armed Services Board of Contract Appeals and the Corpus Christi Ship Channel. Give us a quick overview of the case. Zach Prince This case involved a contract with the Army Corps of Engineers for a dredging project at the Corpus Christi Ship Channel. So the Corpus Christi Ship Channel’s ba…