Escom sees K35 billion project easing outages
Summary by The Nation
1 Articles
1 Articles
Escom sees K35 billion project easing outages
Electricity Supply Corporation of Malawi (Escom) Limited says the delivery of 12 primary containers for the 20 megawatts (MW) Battery Energy Storage System (Bess) on Tuesday is a major step towards easing power rationing. In a statement made available to The Nation, Escom said the containers, expected to be commissioned in February at its Kanengo project site in Lilongwe, have been funded by a $20.245 million (about K35.46 billion) grant from th…