BC Hydro moves forward on plans for unit six of the Revelstoke Dam
Summary by Revelstoke Mountaineer
1 Articles
1 Articles
BC Hydro moves forward on plans for unit six of the Revelstoke Dam
Revelstoke Dam’s sixth and final penstock could finally see an operating unit by December, 2032. Photo by Lys Morton/Revelstoke Mountaineer Construction on unit six of the Revelstoke Dam is slated for spring, pushing back the original anticipated completion date for the final unit. The goal for unit six is to increase capacity for peak needs, adding an estimated 500 megawatts of generating capability. While BC Hydro’s average needs can still b…