Red Electrica Blamed the "Itches of Tension" that the Operators Warned Days Before the Blackout that "Just" There Was Nuclear
4 Articles
4 Articles
LM accesses the blackout audios that disrupt the Sara Aagesen and Red Electric version of what happened on April 28.
Red Eléctrica alluded to the fact that "only" there was nuclear power in the system as the reason for the constant and pronounced variations of electrical voltage that those who warned more than a week before the power outage of 28 April 2025 operators of the Iberdrola power plants who called the system operator to know what was going on. They also did so that same day, hours before the electric zero, when the response given then was that the vo…
The transcripts corroborate that electrical operator technicians attributed the problems to photovoltaics and the lack of nuclear power
The talks sent to the Senate committee show that the system operator knew the network imbalances days before the April 28 blackout and attributed them to photovoltaics and to the lack of nuclear Aagesen calls for elé
Coverage Details
Bias Distribution
- 67% of the sources lean Right
Factuality
To view factuality data please Upgrade to Premium