Another milestone for Mortlake BESS - Utility Magazine
Origin Site Project Manager, Barry Brown, stands next to one of the transformers en route to Mortlake. Image: Origin Energy Origin Energy has taken yet another step forward in the delivery of the large-scale battery at Mortlake Power Station, with two purpose-built 200t transformers arriving on-site. Each transformer, measuring around 9m long and 2.5m wide, can handle up to 180MVA of electrical load. When installed within the Mortlake Termina…