Britain approves 2 gigawatt undersea power cable
The 138km undersea link will carry more secure power and support rising demand, while National Grid prepares for construction planning.
The Department of Energy Security and Net Zero approved National Grid's Sea Link project yesterday, granting a development consent order for a 138km high-voltage electricity connection linking Kent and Suffolk.
Opposition to the project centered on the Minster Marshes, where about 17,000 petition signatories claimed the development threatens a "critical ecological superhighway" home to 37 red-listed species.
Siemens Energy will construct 100ft-tall converter stations in both counties, while Sumitomo Electric manufactures cables at its new £350 million factory in Scotland, expected to create more than 200 skilled local jobs.
Energy minister Baroness Margaret Curran acknowledged "lasting landscape and visual harm" but concluded public benefits outweigh impacts, while wildlife campaigner Nik Mitchell expressed disappointment at the rushed decision.
National Grid expects construction to begin in early 2027 with completion targeted for 2031; project director Adrian Pierssene stated the link will support the electricity network in England and Wales to meet growing demand.