Work continues on Barren County Judicial Center
By MICHAEL CRIMMINS Glasgow News 1 Progress is being made on the new Barren County Judicial Center. During the Project Development Board meeting on Jan. 14 Alliance Corporation Executive Vice President and Chief Operation Officer Tim Geegan said the rammed aggregate piers that were discussed at the last board meeting had been installed and concrete was beginning to be poured. “Concrete has hit the job site,” Geegan said. “There’s a lot to pour b…