Third Bridge of Montería Advances Above the Schedule and Reaches 12.90 % of Execution

Summary by larazon.co
The construction of the third bridge of Montería reached an accumulated physical advance of 12.90 %, a figure that exceeds by 2.52 percentage points the programming established for this stage of the project, which contemplated an execution of 10.38 %. The report was delivered during a technical inspection led by the mayor of Montería, Hugo Kerguelén García, who toured the work fronts to verify the development of one of the most relevant road inf…
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.

1 Articles

The construction of the third bridge of Montería reached an accumulated physical advance of 12.90 %, a figure that exceeds by 2.52 percentage points the programming established for this stage of the project, which contemplated an execution of 10.38 %. The report was delivered during a technical inspection led by the mayor of Montería, Hugo Kerguelén García, who toured the work fronts to verify the development of one of the most relevant road inf…

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe
Father's Day SaleGet 40% off Vantage subscriptions for yourself or a friend.Get Started

Bias Distribution

  • There is no tracked Bias information for the sources covering this story.

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

larazon.co broke the news on Saturday, June 13, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)
News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal