They Ask to Close the Three Floors of an Important Cotton Line and Disengage 243 Employees
5 Articles
5 Articles
The Sindicatura of the bankruptcy of Algodonera Avellaneda asked the Justice to order the cessation of the activities; warned that the production generates losses of up to $814 million per month and that to continue the operations would aggravate the debts
The Justice ordered the gradual and orderly suspension of the production of Algodonera Avellaneda, in Reconquista, in the framework of the bankruptcy process. The decision, signed by Judge Fabián Lorenzini, also ordered the termination of the labor contracts and authorized minimum guards in the three establishments of the firm. The measure seeks to stop [...] The news Algodonera Avellaneda: the Justice ordered to stop the production to avoid new…
With the argument that every day of continuation generates expenses of the contest that are paid with preference and that, in short, supports the mass of creditors, starting with the workers themselves, the Judicial Syndicate in charge of the administration of Algodonera Avellaneda S.A., in bankruptcy since 14 October, has asked that the productive plants be closed and the labor connection with the 243 employees be concluded. The plan is based o…
The Sindicatura presented a report to the Justice in which it recommended the cessation of activities of the Reconquista spinning plant and the ginning plants of Santiago del Estero and Chaco
The Sindicatura of the bankruptcy recommended to the Justice the cessation of activities of Algodonera Avellaneda de Reconquista and the ginning machines of Bandera and General Pinedo. He warned that the production generates losses of up to $814 million per month and that "the fasons only cover salaries", while the debt to the EPE exceeds $9,281 million. The [...]
Coverage Details
Bias Distribution
- 100% of the sources lean Right
Factuality
To view factuality data please Upgrade to Premium