Judge Rules Electricity Grid in Haarlemmermeer Is Full, Data Centre Connection Delayed
2 Articles
2 Articles
Judge rules electricity grid in Haarlemmermeer is full, data centre connection delayed
TenneT has received court approval to pause work on a planned electricity grid connection due to capacity constraints in the power network. A data centre developer near Schiphol challenged the decision in summary proceedings, but the court in Arnhem dismissed the claim and ruled in favour of the grid operator.
News Image dpa A court in Arnhem has ruled in favor of grid operator TenneT in a dispute regarding the connection of a data center at Schiphol. The judge ruled that TenneT is permitted to temporarily halt work on the grid connection due to insufficient capacity on the electricity grid. Project developer Goodman had filed summary proceedings and demanded that TenneT realize the connection. Starting June 1, the company had demanded a penalty of 50…
Coverage Details
Bias Distribution
- There is no tracked Bias information for the sources covering this story.
Factuality
To view factuality data please Upgrade to Premium