Judge Rules Electricity Grid in Haarlemmermeer Is Full, Data Centre Connection Delayed

Summary by NL Times
TenneT has received court approval to pause work on a planned electricity grid connection due to capacity constraints in the power network. A data centre developer near Schiphol challenged the decision in summary proceedings, but the court in Arnhem dismissed the claim and ruled in favour of the grid operator.
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.

2 Articles

News Image dpa A court in Arnhem has ruled in favor of grid operator TenneT in a dispute regarding the connection of a data center at Schiphol. The judge ruled that TenneT is permitted to temporarily halt work on the grid connection due to insufficient capacity on the electricity grid. Project developer Goodman had filed summary proceedings and demanded that TenneT realize the connection. Starting June 1, the company had demanded a penalty of 50…

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • There is no tracked Bias information for the sources covering this story.

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

upday broke the news on Wednesday, April 29, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)
News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal