Tata Steel says U.K. plant’s low-emission project facing delays in securing electricity access
The 3.2 million-tonne project aims to cut site emissions by 90% but needs new grid infrastructure before commissioning can begin.
- Tata Steel's £1.25 billion electric arc furnace project at Port Talbot faces a delay of 6-8 months due to issues securing critical high-power electricity access for the site.
- Backed by £500 million in government support, the initiative aims to reduce site-level CO2 emissions by 90%, replacing historic blast furnaces with a 3.2 million-tonne capacity electric furnace.
- Executive Director and Chief Financial Officer Koushik Chatterjee confirmed National Grid warned of connectivity delays, citing complications with ground conditions, environmental factors, and planning requirements.
- Chief Executive Officer TV Narendran stated the company is working with partners to compress post-commissioning ramp-up schedules and conduct equipment trials to recover lost time.
- Meanwhile, the site recently witnessed a fire incident on June 3, though all personnel were safely evacuated; demolition of existing structures continues as the project moves toward its revised commissioning timeline.
11 Articles
11 Articles
Tata Steel shares dip over 2% as UK project may face 6-8 month delay amid electricity access issues
Tata Steel's ambitious low-carbon steel project in the UK is facing a significant delay. The commissioning of the new electric arc furnace at Port Talbot may be pushed back by six to eight months. This setback is due to delays in securing the necessary electricity infrastructure.
Delay of up to a year before Tata's new electric arc furnace can operate
A delay in getting enough electricity to the Port Talbot site means there is currently a 12-month delay to the new electric arc furnace opening but bosses are confident that could come down
Tata Steel says U.K. plant’s low-emission project facing delays in securing electricity access
While we are working with ESO and National Grid for the new electrical infrastructure, National Grid has formally alerted that the connectivity project is delayed, says Koushik Chatterjee, ED and CFO, Tata Steel.
Tata Steel warns £1.25bn Port Talbot furnace could slip eight months over grid hold-up
Tata Steel has warned that its £1.25 billion electric arc furnace at Port Talbot could be delayed by up to eight months, after National Grid formally flagged hold-ups in connecting the plant to the high-voltage power it needs to run. The new furnace, the centrepiece of Britain’s pivot to lower-carbon “green steel”, had been due to fire up by the end of 2027, replacing the traditional blast furnaces that closed two years ago with the loss of arou…
Coverage Details
Bias Distribution
- 40% of the sources lean Left, 40% of the sources lean Right
Factuality
To view factuality data please Upgrade to Premium







