Published 15 minutes ago • loading... • Updated 3 hours ago
Alberta-to-B.C. pipeline project to increase flow has been completed
A chemical drag-reducing agent lifts the pipeline's capacity by about 10 per cent, to 980,000 barrels a day.
Trans Mountain Corp. completed a project to increase crude flow on its Alberta-to-B.C. pipeline using chemical additives two months ahead of schedule, the Crown corporation said on Friday.
The federal government purchased the pipeline for $4.5 billion in 2018 after Kinder Morgan Canada abandoned the expansion project amid environmental opposition and court challenges.
During the third quarter, the Crown corporation shipped 840,000 barrels per day on average, while drag-reducing agents increased pipeline capacity by about 10 per cent to 980,000 barrels per day.
Trans Mountain began confidential information sessions with potential Indigenous partners in October, as some Indigenous groups have expressed interest in taking a stake in the pipeline.
Alberta is developing the Pacific Link pipeline, but the project faces legal challenges from at least 17 First Nations, including an application to quash the national interest designation.