In a decisive move to accelerate industrial growth in the Petroleum, Chemical and Petrochemicals Investment Region (PCPIR), the Odisha Cabinet on Wednesday approved a revised cost estimate of ₹854.24 crore for the 400/220/33 kV Grid Sub-Station at Paradeep (Ersama) and its associated transmission lines. Originally sanctioned in 2020-21 at ₹637.45 crore, the project cost has […] The post Odisha Cabinet Clears Rs 854 Cr Grid Project to Fuel Parade…