National Highways projects will cost billions more than planned, report finds

Summary by Ground News
Government-owned company National Highways will not be able to deliver dozens of projects within budget, says National Audit Office. 33 schemes are behind schedule by between one month and more than three years, with an average delay of 12 months. Delays have been caused by factors such as the coronavirus pandemic and difficulties obtaining planning permission.