Kathmandu, Sept 14: An 18-kilometre 400 kV transmission line linking Nepal’s New Butwal substation to the Indian border has been completed in about nine months under the US-funded Millennium Challenge Corporation (MCC) programme. The Millennium Challenge Account Nepal Development Committee, MCA Nepal, completed the project within the scheduled timeframe for US$12.8 million, or about Rs2 […]
The post MCC transmission line completed in nine months…
This story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.