Always articulate and thoughtful reader Lew Edwardson left a comment on the IN-SIGHTS article THE HEAT BENEATH OUR FEET. I think it needs to be amplified. Drought in northeast BC continues to be a problem. If the situation of FY 2024 continues, Site C will produce about 3,350 GWh, not the promised 5,100. These numbers suggest the dam's capital cost for each MWh of electricity produced would fall between $142 and $215. Of course, the utility incu…