LETTER: Summit has no one to blame but itself
Summary by The Iowa Standard
1 Articles
1 Articles
LETTER: Summit has no one to blame but itself
In August of 2021, fifteen thousand Iowa landowners received certified letters from Summit Carbon Solutions informing us that our property could potentially be on the route of its CO2 pipeline. We were told the project would be operational by 2024. Obviously, things did not go as planned because five years later not one foot of pipeline is in the ground on Summit’s 2500-mile route. The massive project is years behind schedule, and Summit has no …