Kalashnyk: Kyiv Plans to Add More Than 1.5GW of Extra Thermal Generation
6 Articles
6 Articles
Minister Kalashnik revealed the details soon in Kiev with a view to introducing more than 1.5 GW of additional thermal generation, but this will take place already during the heating season, a statement made by the Ukrainian Minister for Rehabilitation, Infrastructure and Transport Nikolai Kalashnik, reporting to RBK-Ukraine with reference to his post in Telegram. The head of the department checked how the construction of protective equipment fo…
In Kiev, they plan to put into operation more than 1.5 GW of additional thermal generation due to the arrangement of new backup boiler houses.
This was announced by the Minister of Reconstruction, Infrastructure and Transport of Ukraine Mykola Kalashnik.According to him, he inspected the construction of protective structures for critical infrastructure facilities and spare boiler houses in the capital. Together with representatives of the city authorities, customers and contractors, the minister checked the actual state of the works.” There is still a significant amount of construction…
The Infrastructure Minister checked the construction of the stand-by boiler houses and estimated how long the Kievs would wait.
Kalashnyk: Kyiv Plans to Add More Than 1.5GW of Extra Thermal Generation
Minister Mykola Kalashnyk says Kyiv aims to bring more than 1.5GW of additional thermal generation online, including backup boiler houses, with work due in about two months and some installs by end-December.
In Kyiv, it is planned to introduce more than 1.5 GW of additional thermal generation, part of this work is the arrangement of backup boiler houses. - Ukrinform.