Texas Continued Permitting Data Centers After Abbott’s Pause, Report Finds

A report found 35 permitting actions continued after Abbott’s directive, including stormwater approvals and preliminary notices for major gas-powered projects.

FracTracker and Public Citizen identified 35 permitting actions taken by regulators in Texas in the weeks after Gov. Greg Abbott ordered a moratorium. By Dylan Baddour October 19, 2026 This article originally appeared on Inside Climate News, a nonprofit, non-partisan news organization that covers climate, energy and the environment. Sign up for their newsletter here.…

10 Articles

Inside Climate NewsInside Climate News
+3 Reposted by 3 other sources
Lean Left

Texas Continued Permitting Data Centers After Abbott’s Pause, Report Finds

FracTracker and Public Citizen identified 35 permitting actions taken by regulators in Texas in the weeks after Gov. Greg Abbott ordered a moratorium.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 78% of the sources lean Left
78% Left

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

404 Media broke the news in United States on Monday, October 19, 2026.