Texas Continued Permitting Data Centers After Abbott’s Pause, Report Finds
A report found 35 permitting actions continued after Abbott’s directive, including stormwater approvals and preliminary notices for major gas-powered projects.
10 Articles
10 Articles
Greg Abbott’s surprise retreat is a warning for the whole GOP
It’s becoming clear that one of the most potent political issues of this election cycle is the debate over artificial intelligence and the massive data centers powering this rapidly evolving technology. Polling consistently shows that Americans overwhelmingly oppose the rapid buildout of polluting a...
Texas Continued Permitting Data Centers After Abbott's Pause, Report Finds
This article originally appeared on Inside Climate News, a nonprofit, non-partisan news organization that covers climate, energy, and the environment. Sign up for their newsletter here. Regulators in Texas did not stop processing permits for data center projects when Gov. Greg Abbott ordered a pause last month, according to an analysis of public records released […]
Texas Continued Permitting Data Centers After Abbott’s Pause, Report Finds
FracTracker and Public Citizen identified 35 permitting actions taken by regulators in Texas in the weeks after Gov. Greg Abbott ordered a moratorium.
'It Ain't Right:' Texas Said It Would Halt Data Center Permits. The State is Pushing Ahead Anyway
“The Caldwell Technology Park [...] the Stargate facility, and a bunch of other very large hyperscale facilities have gotten regulatory approvals [...] so it's not like a real pause."