Monitoring Desk: Several irregularities have been found in awarding contracts by TMA Mardan. Procurement and Installation of Street Lights The contract was awarded for the procurement and installation of 631 street lights, however only 170 were installed. Lights were not per specifications. The total contract cost was Rs. 50 Million. Rs. 31.0 Million was paid to the Contractor as advance, contrary to contractual requirements. The possible loss t…