Temporary traffic lights and roadworks on Beith Road in Johnstone are expected to remain in place until around the end of September. SGN began the gas main work between the junctions of Greenfeoch Avenue and Quarrelton Road on Thursday 2nd July 2026. The project is estimated to last 64 working days. This gives an expected completion date of around Wednesday 30th September, although the date may change if the work is delayed. The Beith Road roadw…