Construction work on the Sapporo extension of the Hokkaido Shinkansen is facing difficulties in excavating the Sapporo-Otaru Tunnel, which will run beneath Sapporo city. Damage to the excavator blades and poor soil conditions have reduced the excavation speed. Completion of the Sapporo section is now expected to be delayed by 2 years and 5 months from the original estimate, until the end of February 2031. […]