The government announced the start of the process to rent 260 megawatts (MW). 130 MW will be installed at the Enrique García plant and the same amount for what was the Pascuales II plant, for a period of 18 months.
A few months after the start of the stretch, the Ministry of Energy announced the start of the process to hire 260 megawatts (MW) of energy to thermal temporarily, through a system of rent generation of the grid.
Quito, 12 Jun (La Calle).- The Electric Corporation of Ecuador (CELEC EP) started on June 10 an accelerated process to lease between 80 and 260 MW of thermoelectric energy, under the figure of "specific business turn", seeking operativity by December 2025. The measure, which coincides with the end of the next stretch, comes after the controversial cancellation of contracts with the American Progen Industries LLC, now under warning to proceed wit…
This measure seeks to guarantee electricity supply at the national level during the energy transition period, while permanent generation processes are in place.
Coverage Details
Bias Distribution
- 100% of the sources lean Right
To view factuality data please Upgrade to Premium