Google project in Finland halted after 250,000 trees were cut for AI data centers before environmental review
Regulators said Google cleared about 250,000 trees without required environmental reviews and warned of fines if the company does not comply.
- On Thursday, Licensing and Supervision Authority regulators referred Google's Muhos project to police for investigation after discovering roughly five miles of drainage ditches were dug without required advance notification.
- Earlier this month, regulators halted construction at Muhos and Otanmäki after Google cleared 400,000 trees across 330 hectares without completing mandatory environmental impact assessments.
- Ecologist Mari Annala from the Finnish Association for Nature Conservation described ongoing impacts as relentless, while residents protested brown water from the construction site entering the Oulujoki River.
- Google's Finland country manager, Antti Järvinen, apologized for the tree felling, stating the company acted on its "best understanding we had of the legislation at the time" while awaiting the LVV verdict.
- Google faces broader scrutiny from Donald Trump, who urged the company to reconsider its international investments in favor of building artificial intelligence infrastructure within the United States.
132 Articles
132 Articles
Big Tech knocked down 500 thousand trees to build four artificial intelligence centers. After the protests of the citizens the police opened an inquiry. But the victory risks being temporary
Controversy is escalating as Google’s data center construction in Finland is now under police investigation following a halt order from authorities over "illegal logging." According to foreign media reports, including Reuters on the 29th (local time), the Finnish police [investigated] Alphabet's (Google's parent company) Finnish subsidiary
Finland opens an investigation against Tuike Finland Oy, a subsidiary of Google, for alleged environmental damage after cutting more than 300 hectares of forest, about 420 football fields, without any environmental assessment. Regulators ordered the logging to be stopped in October, even though the technology company claims to believe that it has all the permits.
On Google Killing 400,000 Trees to Build Data Centers in Finland
By Caitlin Johnstone – Oct 27, 2026 I don’t know who first coined the saying “If the penalty is a fine, then it’s legal for rich people,” but it certainly applies here. That story about Google killing hundreds of thousands of trees in Finland for its data center project is such a perfect microcosm of […]
To install a giant data centre, Google deforested more than 300 hectares in Finland without waiting for environmental assessments.