  • CenterPoint Energy announced on May 6, 2025, that it has finished burying a total of 400 miles of its electrical cables in Houston, achieving its undergrounding target ahead of the 2025 hurricane season.
  • The undergrounding project is a key component of the Greater Houston Resiliency Initiative, aimed at enhancing the coastal power grid's durability against severe weather and minimizing outage occurrences.
  • CenterPoint aims to underground more than 50% of its electric system, with the GHRI targeting a reduction of over 125 million customer outage minutes annually.
  • Senior Vice President Darin Carroll highlighted the company’s ongoing dedication and openness as they persist in advancing efforts to create the nation’s most durable coastal electrical infrastructure.
  • CenterPoint expects that completing all GHRI milestones by June will further enhance reliability and resiliency, reducing outages caused by weather, vegetation, and vehicle collisions.
Insights by Ground AI
Does this summary seem wrong?

49 Articles

All
Left
2
Center
19
Right
1
Farm Talk NewspaperFarm Talk Newspaper
+13 Reposted by 13 other sources
Center

Greater Houston Resiliency Initiative Phase Two Update: CenterPoint Energy completes nearly 90% of critical resiliency actions to strengthen the grid ahead of 2025 hurricane season

Over the last eight months, CenterPoint has installed 21,975 stronger, more storm-resilient poles; undergrounded 401 miles of power lines; added 4,472 automation devices; cleared 3,741 miles of high-risk vegetation; and installed 84 weather monitoring stations around the Greater Houston area

·Parsons, United States
Read Full Article
Temple Daily TelegramTemple Daily Telegram
+33 Reposted by 33 other sources
Center

GHRI Phase Two Update: CenterPoint Energy completes 100 percent of undergrounding milestone; 400 miles of strategic power line undergrounding completed ahead of 2025 hurricane season

Underground power lines installed ahead of schedule, with all Greater Houston Resiliency Initiative (GHRI) Phase Two resiliency actions on track to be completed by June 1

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 86% of the sources are Center
86% Center
Factuality

To view factuality data please Upgrade to Premium

Ownership

To view ownership data please Upgrade to Vantage

KWWL broke the news in Waterloo, United States on Tuesday, May 6, 2025.
Sources are mostly out of (0)