FOTO-VIDEO ☆ Sibiu Motorway – Pitești: Mobilization on the Boită – Cornetu Section "Very Much to Be Desired"
5 Articles
5 Articles
Even if the works on Lot 2 of the A1 Sibiu-Pitești motorway, the one between Boită and Cornetu, have advanced in recent months, the mobilization of the Turkish constructor continues to leave to be desired, as the Association Pro Infrastructura states. The representatives of the association also transmit and that, although Mapa-Cengiz invokes the lack of authorizations as the reason why mobilization is not [...] The post Mobilizing the constructo…
The works on the Boița-Cornetu section of the Sibiu-Pitești Highways advance at a rate considered insufficient by the Association Pro Infrastructure. The organization claims that, although the Turkish manufacturer Mapa-Cengiz has started work on some of the important structures, the general mobilization of the 31,33 kilometers still leaves to be desired. According to Pro Infrastructure, of the 48 viaducts and bridges, more [...]
CNAIR Director General, Cristian Pistol, presents images of the Sibiu – Făgaraş motorway, from the trunks between Boita and Arpaşu de Jos! The Sibiu – Făgaraș motorway (A13), in total length of 68 km, is built by Turkish entrepreneur Makyol and has to be completed in 2028. The Tronson 1 (Boita – Avrig), in length [...]
Mobilisation of the Sibiu – Făgaraş Highway, built by the Turkish company Makyol, between Boită and Arpașu de Bass, numbers more than 1,000 workers and more than 500 machines, transmits the director general of the Cristian Pistol Road Company. According to him, the 1st section (Boită – Avrig), in length of 14.25 km, has a [...]
The works at the Sibiu–Făgaraş motorway advance on all four sections, and the Avrig–Arpașu de Jos sector exceeded the 50% threshold.