Fort Walton Beach Landing Park phase two construction targets mid-December completion
Summary by getthecoast.com
1 Articles
1 Articles
Fort Walton Beach Landing Park phase two construction targets mid-December completion
The second phase of the $8 million Fort Walton Beach Landing Park renovation is targeting a mid-December completion after city officials resolved communication issues that had delayed construction. City Manager Jason Davis said there had been a disconnect between GLC Contracting’s team and city staff, resulting in the contractor waiting for instruction for over 100 days. The issue was addressed during a meeting last week. “I asked going forward…