FCC bars court intervention in Nai Gaj Dam project until completion

The court said disputes must follow the contract’s mechanism and directed WAPDA to act on any contractor request within 15 days.

Court says SHC overlooked contractual dispute procedures and relevant WAPDA and NAB laws