FCC bars court intervention in Nai Gaj Dam project until completion
The court said disputes must follow the contract’s mechanism and directed WAPDA to act on any contractor request within 15 days.
4 Articles
4 Articles
Constitutional Court overturns SHC rulings in Nai Gaj Dam case
ISLAMABAD: The Federal Constitutional Court (FCC) has ruled that High Courts cannot use their constitutional jurisdiction under Article 199 of the Constitution to resolve purely contractual disputes or rewrite agreements, arbitral awards or court decrees between contracting parties.
Federal Constitutional Court Clears Legal Hurdles Delaying Nai Gaj Dam Project
The Federal Constitutional Court (FCC) has cleared major legal hurdles delaying the Nai Gaj Dam project by overturning Sindh High Court rulings that allowed the contractor to claim price escalation beyond the original contract. The court also directed that the remaining work be completed under the original agreement, the arbitral award, and the September 21, 2021 memorandum of understanding. In a 21 page judgment issued on Monday, a two member b…
Coverage Details
Bias Distribution
- 34% of the sources lean Left, 33% of the sources are Center, 33% of the sources lean Right
Factuality
To view factuality data please Upgrade to Premium